The flowtime of the last job in a single work center’s schedule is 7 days. What is the makespan of this schedule?

Relax

Respuesta :

Tundexi
Tundexi Tundexi
  • 14-01-2021

Answer:

7 days

Explanation:

Makes-pan means the time it takes to complete a schedule. Last job took 7 days to complete and it was a single job, which means its makes-pan was 7 days as well.

Answer Link

Otras preguntas

what two groups fought the civil war? who led them? why were they fighting?
The last time I asked you, I really got a lame excuse, I know that you lied. Choose the selection in which the sentence is properly punctuated. A) NO CHANGE
When was the first peacetime conscription bill enacted in the United States?
Lord of the flies what does the island symbolize
Because of Hitler's anti-Jewish laws, which of these occurred? A. The Axis powers joined together as allies. B. The Holocaust ensued, killing over six million J
Suppose two chemicals are reacted together. It takes 750 kJ of energy to break the bonds of the reactants and 1050 kJ of energy are released by the formation of
Define a variable. How does a variable relate to a constant?
midpoint of the line with endpoints of (-1,2) and (7,3)
factor completely 3x^2-24x^2 show all work
Why is the world round