Respuesta :
Question Completion:
The speed boat requires 2 hours in fabrication and 1 hour in assembly. Â The bass boat requires 1 hour in fabrication and 2 hours in assembly.
Answer:
Bardot Marine Company
A. Determination of the total number of budgeted direct labor hours in each department:
               Speed boats   Bass boats  Total hours
Direct labor hours:
Fabrication         10,000      5,000      15,000
Assembly          5,000      10,000      15,000
Total             15,000      15,000      30,000
B. Determination of the departmental factory overhead rates for both departments:
Overhead rate = $367,500/30,000 = $12.25
Fabrication $ per dlh  = $12.25
Assembly $ per dlh = $12.25
C. Determination of the factory overhead allocated per unit for each product using the department factory overhead allocation rates:
Speedboat: $ per unit  = $36.75 ($12.25 x 3)
Bass boat: $ per unit = Â $36.75 ($12.25 x 3)
Explanation:
a) Data and Calculations:
Total factory overhead = $367,500
                  Speed Boats     Bass Boats
Budgeted units         5,000         5,000
Hours per unit          3             3
Total direct labor hour  15,000        15,000
Fabrication             2 hrs          1 hr  Â
Assembly              1 hr           2 hrs
Total direct labour hours:
Fabrication          10,000         5,000
Assembly            5,000         10,000