A bucket that has a mass of 30 kg when filled with sand needs to be lifted to the top of a 30 meter tall building. You have a rope that has a mass of 0.3 kg/m that must be secured to the bucket. It takes 1 meter of rope to secure the bucket. Once the bucket reaches the top of the building it only has mass 15 kg because there was a hole in the bottom and sand was leaking out at a constant rate while it was being lifted to the top of the building. Find the work done lifting the bucket (sand and rope) to the top of the building.

Relax

Respuesta :

Answer:

765 J

Step-by-step explanation:

We are given;

Mass of bucket = 30 kg

Mass of rope = 0.3 kg/m

height of building= 30 meter

Now,

work done lifting the bucket (sand and rope) to the building = work done in lifting the rope + work done in lifting the sand

Or W = W1 + W2

Work done in lifting the rope is given as,

W1 = Force x displacement

W1 = (30,0)∫(0.2x .dx)

Integrating, we have;

W1 = [0.2x²/2] at boundary of 30 and 0

W1 = 0.1(30²)

W1 = 90 J

work done in lifting the sand is given as;

W2 = (30,0)∫(F .dx)

F = mx + c

Where, c = 30 - 15 = 15

m = (30 - 15)/(30 - 0)

m = 15/30 = 0.5

So,

F = 0.5x + 15

Thus,

W2 = (30,0)∫(0.5x + 15 .dx)

Integrating, we have;

W2 = (0.5x²/2) + 15x at boundary of 30 and 0

So,

W2 = (0.5 × 30²)/2) + 15(30)

W2 = 225 + 450

W2 = 675 J

Therefore,

work done lifting the bucket (sand and rope) to the top of the building,

W = 90 + 675

W = 765 J