Answer:
The total cost for the job is $5086
Explanation:
Given that:
Direct materials cost                     $3044
Direct labor-hours                       46 labor hours
Direct labor wage rate                    $15 per labor-hour
Machine-hours                          104 machine-hours
Overhead rate                           $13 per machine-hour
Therefore:
Direct labor = Direct labor-hours × Direct labor wage rate
∴ Direct labor =  46 labor hours × $15 per labor-hour = $690
Manufacturing overhead = Machine-hours × Overhead rate
∴ Manufacturing overhead = 104 machine-hours × $13 per machine-hour
Manufacturing overhead = $1352
The total cost for the job = Direct materials cost + Direct labor + Manufacturing overhead
∴ The total cost for the job = $3044 + $690 + $1352  = $5086
∴ The total cost for the job = $5086