Assume that it is customary in the industry to bid jobs at 150% of total manufacturing cost (direct materials, direct labor, and applied overhead). What would the bid price have been if departmental predetermined overhead rates had been used to apply overhead cost

Relax

Respuesta :

Answer:

Some financial details with which to calculate the bid price are missing,find them in the attached question.

The bid price if the predetermined overhead rates have applied is $112,473.00 as shown below

Explanation:

a) Plantwide Overhead Rate = Manufacturing overhead/direct labor cost=$1,543,610.00/$947,000.00

Plantwide Overhead Rate = $1.63

Total Manufacturing Cost = Direct Material + Direct Labor + overhead applicable

Total Manufacturing Cost = $18,700.00+$21,400.00 + $(21400*1.63 )

Total Manufacturing Cost = $ 74,982

Bid Price = Total Manufacturing Costs *1.5(150%)

Company's Bid Price = $74,982.00*1.5

Company's Bid Price = $ 112,473.00