
Respuesta :
Answer:
2021
revenue         2,666,667
we have cost for  2,000,000 Â
income for         666,667
2022
revenue           3.278.400‬
cost              2,500,000  Â
income              778.400‬
2023
revenue      2,054,933‬
cost         3,800,000 Â
loss          1,745,067‬
Explanation:
2,000,000/ (2,000,000 + 4,000,000) = 1/3
in 2021 a third of the contract was complete therefore we recognize a third of revenue:
8,000,000 x 1/3 = 2,666,667
we have cost for  2,000,000
income for         666,667
2,500,000 / (2,500,000 + 3,600,000) = 0,4098
we recognize revenues for 40.98 of the total contract value.
8,000,000 x 40.98 = 3.278.400‬
cost              2,500,000  Â
income              778.400‬
2023
we recognize the remaining revenue.
8,000,000 - 2,666,667 - 3,278,400 = 2.054.933‬ revenue
cost 3,800,000
loss  1,745,067‬
If on February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. The amount of revenue and gross profit or loss to be recognized in each of the three years will be: Â Â Â
Revenue to be recognized      Â
- 2018 $2,833,050 Â Â
- 2019 $1,889,550 Â Â
- 2020 $3,777,400
Gross profit (loss) to be recognized
- 2018 $833,050 Â Â
- 2019 -$610,450 Â Â Â Â
- 2020 -$22,600
                           2018         2019           2020   Â
Billings during the year       $2,500,000    $2,750,000   $3,250,000
                            2018         2019           2020   Â
Costs incurred during the year   $2,000,000   $2,500,000   $3,800,000
Cumulative costs to date        $2,000,000   $4,500,000    $8,300,000
Add estimated costs to complete $4,000,000 Â Â $3,600,000 Â Â Â Â Â Â Â $0 Â Â Â
Estimated total costs           $6,000,000  $8,100,000    $8,300,000
2020 Billings during the year=$8,000,000-$2,500,000-$2,250,000
2020 Billings during the year=$3,250,000
2019 Cumulative cost to date=$2,500,000+$2,000,000
2019 Cumulative cost to date=$4,500,000
2020 Cumulative cost to date=$4,500,000+$3,800,000
2020 Cumulative cost to date=$8,300,000
Percentage of completion
2018   $2,000,000/$6,000,000×100=33.33% Â
2019    $4,500,000/$8,100,000×100=55.56%   Â
2020   $8,300,000/$8,300,000×100=100%
Contract price of this project             $8,500,000
($2,500,000+$2,750,000+$3,250,000)
Less cumulative cost to date till 2020 Â Â Â Â Â $8,300,000
Contract estimated gross profit (loss) Â Â Â Â Â $200,000 Â
                            2018         2019           2020  Â
Contract value completed       $2,833,050  $4,722,600   $8,500,000
Less revenue recognized        $0         -$2,833,050  -$4,722,600   Â
Revenue to be recognized       $2,833,050   $1,889,550   $3,777,400
Less cost incurred              $2,000,000   $2,500,000   $3,800,000
Gross profit (loss) to be recognized $833,050 Â Â -$610,450 Â Â Â Â -$22,600
2018 Contract value completed = ($8,500,000×33.33%=$2,833,050)
2019 Contract value completed = ($8,500,000×55.56%=$4,722,600)
2020 Contract value completed =($8,500,000×100%=$8,500,000)
Learn more here:
https://brainly.com/question/15540744