The critical path of a network is the A. shortest time path through the network. B. path with the most activities. C. longest time path through the network. D. path with the fewest activities.

Relax

Respuesta :

Answer: Option [C] : The longest time path through the network.

Explanation:

The critical path of a network is the longest time path through the network.