Answer:
direct labor cost variance = 14150 U
correct option is C) $14,150 U
Explanation:
given data
labor hours LH Â = 1,000
actual labor cost  AL = $48.15 per hour
standard cost  SC = $34 an hour
labor cost totaling = $26,000
to find out
direct labor cost variance
solution
solution
we will apply here equation for direct labor cost variance that is
direct labor cost variance = LH × ( AL - SC)   ..............1
here  LH is labor hours and AL is actual labor cost and SC is standard cost so put all these in equation 1
we get
direct labor cost variance = 1000 × ( 48.15 - 34 )
direct labor cost variance = 14150 U
correct option is C) $14,150 U