Using the PERT estimate, calculate the estimated duration of an activity given:
Optimistic Estimate = 21 days
Pessimistic Estimate = 110 days
Most Likely Estimate = 55 days
a) 62.5 days
b) 74 days
c) 65 days
d) 68.5 days

Relax

Respuesta :

Otras preguntas

The expression below describes the number of organisms in a population of bacteria that is undergoing exponential growth. In this expression, r is the amount of
i need help with my problems cuz i am a girl and i am having mood swings and i need help cuz i don't know why i am having mood swings. btw i am 12 and a girl​
a2+14a+49 please help me​
Cornwallis surrendered to Washington at___.​
in three sentences, give the difference between the roles and function of counselors​
What is the goal of the Flat earthers (the one who believes that the earth is flat)?
As the leader of Iraq in the 1990s, Saddam Hussein
this is my question :>
Wanna play among us I will give u the code
what is the the slope of the line through (2, -2) and (9, 3)