
Answer:
A. Â
0.833
Explanation:
m = 3
Arrival rate, ra = 45 per hour
Service rate, re = 18 per hour per lane
Utilization factor = ra/(m.re)
              = 45/(3*18)
              = 0.833
Therefore, The utilization factor of the system is 0.833